electric generator boiler
Some of the existing in-plant equipment will be retrofitted, modifications made in auxiliary equipment/components and major overhauls undertaken. As electric generator boiler is the most important component of a coal-fired power plant, the existing oil-fired boilers at Jamshoro will be replaced with 1x400MW supercritical coal-fired steam generator at a cost of $740 million.
Tubular steam electric generator boiler gas boiler plant in Henan: Iannone fuel boiler steam generator exemption certificate for the use of the unique design of the internal structure of the series water volume is less than 50L, within the exemption permits boiler use a range of countries that use the certificate without going through the boiler . Furnace is equipped with a built-in separator, to solve the problem of steam with water, and more to ensure the quality of steam. Fuel steam generators advanced automatic control system for the automatic control of boiler operation, all operating states are available at a glance on the LCD screen. You can observe in the display to the burner working condition, biomass burning furnace gas state level Tubular steam boilers, boiler plants current temperature, feed pump running status, DZH type moving grate biomass steam boiler. Failure alarm status, allowing you to keep abreast of boiler operating conditions, use more confidence. Fool a control key, a single button press enter the automatic running, LSH vertical biomass steam boiler, all the safety devices are to work without special duty, the operator more secure, are to work Tubular gas steam boiler worry.
The corresponding relationship between the power generation capacity MW and the electric generator boiler capacity of tonnage is as follows.
1. Medium pressure boiler; boiler evaporation: 75t/h; main steam parameter 3.82MPa/450°C. Supporting steam turbine generator set capacity 12MW
2. Medium pressure boiler; boiler evaporation: 130t/h; main steam parameter 3.82MPa/450°C. Supporting steam turbine generator set capacity 25MW
3. High-pressure boiler; boiler evaporation: 220t/h; main steam parameter 5.4MPa/540°C. Supporting steam turbine generator set capacity 50MW
4. High-pressure boiler; boiler evaporation: 260t/h; main steam parameter 5.4MPa/540°C. Supporting steam turbine generator set capacity 60MW
5. High-pressure boiler; boiler evaporation: 410t/h; main steam parameter 5.4MPa/540°C. Supporting steam turbine generator set capacity 100MW
6. Ultra-high pressure boiler; boiler evaporation: 440t/h; main steam parameter 13.7MPa/540°C. Supporting steam turbine generator set capacity 135MW
7. Subcritical boiler; boiler evaporation: 1025t/h; main steam parameter 14.7MPa/540°C. Supporting steam turbine generator set capacity 300MW
8. Supercritical boiler; boiler evaporation: 1900t/h; main steam parameter 26.2MPa/566°C. Supporting steam turbine generator set capacity 600MW
We produce steam electric generator boiler is a very important part of the device, this provides a quick way to our gas steam boiler, after use, we found an excellent energy-saving effect boilers, flue gas discharge temperature is lower than the previous boiler equipment many, in line with national environmental provisions of the boiler equipment. --customer feedback